** PRESS RELEASE **


From the beautiful brick Castle Rock fire station to elaborate churches and schools and a variety of other Colorado landmarks, MW GOLDEN CONSTRUCTORS is known for an amazing ability to give each structure an individually crafted sense of place.

KeyBank National Association Inc. - Thornton Branch

Built in 2009, this ground up, new construction project included site work, landscaping, concrete, masonry, metal fabrication, framing, architectural woodwork, doors and windows, interior finishes, appliances, window treatments, and mechanical, Electrical and plumbing packages. Construction was completed in August of 2009.

The New Paonia Public Library

This project consisted of new construction for an 8,000 sq-ft public library designed for LEED Certification. The new facility incorporates sustainable building features, including a geo-thermal field for heating and cooling, natural lighting and optimum energy efficiency.

On October 2nd of 2009 The New Paonia Public Library was awarded a Gold Hard Hat Award by Colorado Construction Magazine for Outstanding Green Project of the year.

Parker Fire Station No. 77

The new 10,300 sq-ft, $2.7 million dollar facility creates an extension of community service in eastern Douglas County, reducing call times and increasing availability of emergency services to the local public service system.

The new building incorporates apparatus bays, a basement, mezzanine, deck, sleeping rooms, a dining and kitchen area, overhead doors, two 20,000 gallon water storage tanks, a 1,000 gallon septic tank, 750 gallon sand/oil interceptor and a water well.

Douglas County West Service Center Freezer Addition & Bus Wash

The project included the installation of a 5000 sq-ft freezer addition that connects to the existing 20,000 square foot warehouse which will be remodeled. The project also included the addition of a new bus wash facility including upgrades to the existing project site.

New World Millworks

This $4.6 million, 98,000 Square Foot Manufacturing Facility features tilt-up wall construction, manufacturing space with truck docks, a veneering area and a paint booth. The MW GOLDEN CONSTRUCTORS Design-Build team had approximately 10 months from groundbreaking to move-in. Colorado Construction Magazine honored MW GOLDEN with a 2007 Silver Hard Hat Award in the Outstanding Design-Build project category for the firm's ability to successfully manage a complex project with the characteristic inginuity and flexibility it's clients have come to trust.

The Hess Well Facility

As the population of Denver's southeast suburbs continues to grow, so has the need for a state of the art water pumping and treatment facility. MW GOLDEN worked in careful coordination with Integra Engineering to create a 35,000 gallon well house designed to bring in raw water from the Arapahoe aquifer, treat the water, then pump it out to the greater Parker area. MW GOLDEN constructed more than 800 feet of 12-inch raw and finished water line and installed three vertical turbine variable speed pumps that each pump up to 800 gallons per minute. The 3,000 sq-ft. integrated color block structure features a pre-finished standing seam metal roof with a synthetic stone base.